1st Week of September
Material is starting to arrive. The garage is the delivery point and staging area. Right now we have a lot of exterior trim board material stacked up just outside the garage, with the basement stairs, exterior doors, piping, and plumbing fixtures sitting inside the garage.
|
Stacked exterior trim boards |
|
boxed Plumbing fixtures |
|
Front doors! |
But the material does not sit around for very long. Most of the exterior doors have now been installed.
|
Rear door & most of the window trim |
And the last of the windows have been installed as well. This included a couple of octagonal windows - one on the west side of the house and one on the east side of the house.
More ductwork is upstairs. A lot of the ducts are installed, as well as most of the plumbing. Today Steve and I spent four hours at a tile store making final selections for all the bathrooms. Tomorrow we meet with the plumber to set faucet locations. So progress is being made on many fronts.
No comments:
Post a Comment