1st Week of September
Material is starting to arrive. The garage is the delivery point and staging area. Right now we have a lot of exterior trim board material stacked up just outside the garage, with the basement stairs, exterior doors, piping, and plumbing fixtures sitting inside the garage.
|  | 
| Stacked exterior trim boards | 
|  | 
| boxed Plumbing fixtures | 
|  | 
| Front doors! | 
 But the material does not sit around for very long.  Most of the exterior doors have now been installed.
|  | 
| Rear door & most of the window trim | 
 
And the last of the windows have been installed as well.  This included a couple of octagonal windows - one on the west side of the house and one on the east side of the house. 
More ductwork is upstairs.  A lot of the ducts are installed, as well as most of the plumbing.  Today Steve and I spent four hours at a tile store making final selections for all the bathrooms.  Tomorrow we meet with the plumber to set faucet locations.  So progress is being made on many fronts.  