1st Week of December
I have gotten a few requests to see pictures of the bathrooms. It's hard to take a picture of a small room, which is one of the reasons I have hesitated to show the bathrooms. Also, these rooms have continued to be "works in progress". Unfortunately the selections of bathroom vanities became a real problem, and are part of the reason for the delay in completion of the house :o(
|
Master Bath Shower & Tub |
One of the biggest gaps to completing the house is plumbing work. The electrical, mechanical and plumbing subcontractors like to come back only when there is a lot of work for them to do. They really like to limit the number of times they come to the house. The plumber has not wanted to come back to the house to complete his work until everything was ready for him. And that meant the vanities and their countertops need to be in place. The bathroom vanity countertops are supposed to be installed tomorrow; my fingers are crossed. The plumber is supposed to work over the weekend to complete all remaining plumbing work. Most of the shower fittings still need to be installed, as well as all the lavatory sink faucets.
|
Master Bathroom vanities - waiting for the countertops |
There are several small details left to finish in the bathrooms. The recesses in the showers need a "ledge", and the glass partitions and thresholds need to be installed at the showers. We also still need mirrors for the Master Bathroom. But I will be delighted to get countertops and working faucets.
No comments:
Post a Comment