Saturday, August 31, 2013

Cobblestone, Monterey Taupe and Amazing Gray

September 1st

Our construction site has been pretty quiet for the past couple of weeks.  But while there hasn't been much construction happening there has been a lot of planning and decision-making.  You would think I would not be surprised by all the decisions that have to be made in the course of a construction project, but I feel like every time I turn around there are more selections and/or decisions to be made.  There's a lot of pressure to decide on something you will literally live with!

With the Tyzek wrap up, the Builder was ready to purchase the exterior wall materials.  We needed to make a final decision about the house siding material, choosing between vinyl siding, insulated vinyl siding, or cement board siding.  Of couse there is a price tag associated with each of these choices.  (The costs are never far from our minds.)  Integral with the siding selection was the stone selection.  The colors need to compliment each other.  While we were pondering the wall finish materials the Builder asked for a paint color for the foundation walls.  He wanted to paint the foundation walls before back-filling the dirt around the house.  I said "I can't pick the foundation paint color until we pick the siding colors!"  It's all relatived.  So all of a sudden we had lots of decisions to make, and I felt like I was holding up progress.

Partial Elevation of the Front of the House
There are two siding materials to select - the horizontal siding to go on the main walls of the house at the sides and rear, and the "shake" siding that will go on those areas of the house that project from the main planes of the house.  We decided that we want the shake siding to be a slightly darker color than the typical siding boards.  To complicate matters more, the color selections for materials shown within manufacturers' brochures is NEVER accurate.  So the Builder had to find real samples for color selection. 
Finally, we decided to use a fiber cement board siding product called "HardiPlank".  The horizontal siding will be "Cobblestone" color, and the shakes will be "Monterey Taupe".




Once the siding types and colors were selected I picked the paint color for the basement walls - Sherwin Williams "Amazing Gray".

Basement wall, painted "Amazing Gray"


Thursday, August 22, 2013

A Room With a View

Somehow we lucked out when we bought our house at 10208 Carol Street.  Not only was the house lot size an acre, but the property came with an "out lot".  When our neighborhood was developed our house was the first one to be built.  Most likely all the planned house lots were laid out, and platted, before our house was built.  The house lots are all about an acre in size, and they curve in a rough "U" shape.  The space kind of left over, in the middle, was designated the Out Lot, and tagged onto the first house property.  I believe it is called an Out Lot because it cannot be built on.  Our neighbors (original owners of their home) have told us that the developer could not get that lot to "perk", meaning they could not qualify the land to support a septic field.  (Great Falls does not have public water or sewer services.)

A Forest thru the Trees

Having the Out Lot as part of our property gives us a lot of privacy (no pun intended).  In the summer you cannot see any of the houses that surround us.  And of course, it gives us that much more land.  When we first moved in the front yard was a dense grove of trees, and the back of the house was a forest - no yard at all.  Over the years Steve poured a lot of sweat into selectively cutting down trees, digging up roots, renting and loading dumpsters to haul all the wood away, bringing in topsoil and grading, and finally creating grassed yards for us in the front, back and side of the house.

Fallen trees, over the tennis court
Of course, once we had selectively removed trees and created lawns storms started to wreck havoc, literally.  It started the year of Hurricane Isabella.  Our trees were being uprooted.  The year of Hurricane Isabella we lost about six trees.  Since then every year we seem to lose anywhere from one to three trees.  It's very sad to see, but the trees have had a good life and for many of them their time had come. 

But the lot still remains well-forested, particularly within the Out Lot portion.  Looking out to our back yard has always been enjoyable.  We knew when we started designing the house the focus of the primary family spaces - Family Room, Eating Space and Kitchen - would be the back yard.  So a lot of our attention in the design centered on the Family Room.  There are lots of windows in the Family Room - 11 to be exact!

Drawing of the Family Room & Eating Area, looking toward the backyard
Spatial proportion is important to understand in Architecture.  The sense that a space "feels right" comes from the space having the proper sense of scale and balance.  I fretted over the size of our Family room.  I wanted it to be just right; not too big and with a sense of intimacy.  The jury will remain out, as to how successful we have been in our design attempt, until the space is completely finished.  But so far I am having very good feelings about this room.

The room starts to take shape (looking towards stairs)


The "view", without the windows
 It was neat to have such a big expanse of open view, before the windows went in.

Looking down to the Family Room
Footnote:  As the drawing through the Family Room shows above, we did not plan to have an octagonal window in the upper part of the wall.  One day we took Alex over to the house.  We walked up to the balcony and looked down on the family room.  Alex asked if there were going to be any windows in the upper portion of the wall?  I said "no".  He looked at me and said, "you won't see the outside from up here then."  The next day the builder asked "Don't you want windows in the upper portion of the wall?"  Everyone's an Architect!

So I guessed we caved.  Steve and I played around with drawing in all sorts of window sizes and shapes.  In the end the only thing I was comfortable with was the octagonal window.  It is exactly at eye-level from the balcony.

It's that issue of balance.  I am concerned about how the wall will look from the outside as much as from the inside.

Looking toward the Family Room from the backyard



Wednesday, August 14, 2013

The White House

2nd Week of August

One of the most effective ways to provide additional weather protection and increase the energy efficiency of a home is to create a continuous air and moisture barrier around the entire house; in other words, "wrap it".  One material has been around for so long as to become the industry standard.  Much like Kleenex, "Tyvek" has become so frequently used that it has become part of a builder's everyday vocabulary when talking about weather-protective enclosures.

our "white house"

With our house wrapped in "tyvek" we now have a "white house" .  .  .  .  for a little while, until the stone veneer and vinyl siding materials are installed, and cover it up.  I hope that happens very soon.

Wednesday, August 7, 2013

Halfway Home

We have hit another milestone.  We signed our contract with the builder on May 2nd, with the agreement that he would build our house within 6 months.  On August 2nd we hit the halfway point.

Halfway done
The builder is probably 35 - 40% complete with the house.  The inside is just framing at the moment.  In the next couple of weeks the dirt will be backfilled around the house, and the mechanical and plumbing contractors will start doing their layouts of ductwork and piping.  And then of course there is the stonework!  There is still a lot to be done, but progress is steady.  The next three months will be just as interesting as the last three months, I'm sure.

Tuesday, August 6, 2013

A Roof Over our Heads

Our Contractor has had a couple of major milestones in mind since our project started, and they were both very much weather-related.  First he was focused on "getting out of the ground", i.e. getting all the concrete poured, thus getting us out of a potential mud hole.  Second he focused on "getting us under roof", i.e. framed and weather-protected.  Until the roof is on the house several of the trades cannot start their work. 

It took about three weeks to get all the structural wood framing in place, along with the exterior wall sheathing.  As soon as the plywood roof sheathing had been installed the roofing contractor arrived and laid a layer of underlayment roof felt. This only took a day.

Layer of roof felt is installed first
Of course, before the roof could be installed we had to pick a shingle color!  We had already specified the type of shingle we wanted, and the contractor was planning to provide "Certainteed" Landmark series architectural style shingles.  We looked at half-a-dozen shingle colors, and drove around the neighborhood looking at roofs, to get comfortable with the grey/brown color we were leaning toward.  We know what color we want for the stone at the front of the house, and we have the color range for the siding narrowed down but not selected.  We want the shingle color to compliment both the stone and siding, but without having real samples of those materials it was hard for us to select the roof shingle color.  We decided on "Driftwood", but couldn't help being unsure until we actually saw it in place. 
Landmark series, "Driftwood" shingles

Roof shingles arrive
The carpenter was working just a day ahead of the roofers, to get all the roof overhangs, edge details and fascia boards in place.  From start-to-finish the roofing took about five days to install.

Half the shingles are in place, on the main roof of the house

Somehow it didn't register that at the same time the roofing was going up the windows would also be installed.  One day we walked over to see the roof progress and more than half the windows had been installed!  One of the features of our house that makes it a little different from a "typical" house is the preponderance of windows.

Roof shingles AND windows!
So now we are almost entirely "protected" from the weather.  We still need the doors, which are due to arrive in about 2 weeks.
 
More windows than wall area?
The irony to me is that Steve and I started down our l-o-n-g road to a new house with the simple desire to replace the roof and windows in our house.  Well, it took awhile, but we finally have a new roof and new windows.